8.3 MWp rooftop PV system with roof waterproofing in Valence

In 2026, Centroplan France commissioned an 8.31 megawatt-peak (MWp) rooftop PV system in Valence. Its 18,468 modules are forecast to generate 10,562 MWh of solar power per year, all of which is fed into the grid.

8.3 MWp rooftop PV system with roof waterproofing in Valence
Capacity
8,310 kWp
Location
Valence
Country
Frankreich
Year
2026

Challenge

Before the first module could be installed, 60,000 m² of roof had to be waterproofed. Waterproofing, installation and grid connection at medium-voltage level were closely interlinked and required tight coordination between all partners involved. Added to this were the technical and safety requirements that come with a project of this scale.

Solution

First, a waterproofing membrane was laid across the full 60,000 m² of roof. Then 18,468 modules of 450 Wp each were installed on a mounting system designed to match the waterproofing precisely. The system is connected to the grid via two transformer substations and one grid connection substation. After seven months of construction, including waterproofing, it went into operation.